How It’s Looking: Remuera

 

Platform modifications at Remuera train station are part of the work going on in Auckland’s Summer rail development.

Exactly a year ago at Remuera during the 2010 Summer work, tracks were lowered so the electric wires could be placed under the tunnel at the station -Photos of that are here.

Here is how today’s work is looking:

Summer Rail Programme series: How It’s Looking At…

Greenlane

The new DL locos

Glen Eden

Baldwin update with 10 days to go

St George update

Baldwin update

Rossgrove Tce and Baldwin update

Homai Browns Rd, Manurewa

Church St East, Penrose

Waterfront trams

Bridge St, Papatoetoe

St George St, Papatoetoe rail bridge replacement

Remuera

Newmarket

Baldwin Ave

Quay Park

Purewa Eastern Line track work

Manukau’s new station

CBD Shared Spaces

Tags:

 
 
 

15 Comments

 
  1. patrick says:

    hi Jon
    Thanks for the photos. Any chance of seeing what’s happening at Papatoetoe. Apart from the new bridge they are replacing sleepers and possibly working on the platform

  2. Jon C says:

    @Patrick I am holidaying in Brisbane but as you notice my little helpers are out covering the various work areas so watch this space!

  3. Feijoa says:

    What are they doing here this year? Is the platform being extended along beside the station building or is it improvements to the current stretch?

  4. Simon says:

    They are changing the platform height because after lowering the tracks last year Kiwirail discovered that a particular type of freight wagon didn`t have enough clearance height going past the station anymore! Doh!

  5. patrick says:

    hi Jon
    thanks, I’ll be watching this space!!

  6. kel says:

    Please tell me that little hut at the end will be pulled down soon… :P

  7. Matt L says:

    Kel - That hut is a historic building so it can’t be pulled down, in fact it has just been repainted and the station building itself will get the same treatment when the trust that looks after them gets enough money to do the job.

  8. Jon C says:

    @Kel, the Remuera Railway Station Preservation Trust has done a great job preserving the signal box. I’m thrilled the trust is now fundraising to do up the adjourning railway station building, which is closed off to the public station area. We don’t want only modern shelters around the network when we could also see reminders of where Auckland rail came from.
    http://www.aktnz.co.nz/2010/10/21/remuera-signalbox-shining-example/

  9. Ian M says:

    I wonder how much it would cost to lift the station building up, so that the platform would be at the correct level. The Preservation Trust has already done a wonderful job on the signal box.

  10. Finn says:

    I think, keep the Station Building and extend the platform over it just like Swanson.
    Are they doing work on Greenlane Station?

  11. Mike F says:

    Nothing at Greenlane. Still the unloved station.

  12. Finn says:

    Thats a shame, Greenlane really does need a clean-up.

  13. Mike F says:

    Finn
    Enabling works start at Greenlane station February-March with the main construction of the platform extension being planned for April - May.

 

Leave a Comment

 




XHTML: You can use these tags:
<a href="" title=""> <abbr title=""> <acronym title=""> <b> <blockquote cite=""> <cite> <code> <del datetime=""> <em> <i> <q cite=""> <strike> <strong>